Saturday Morning- The Dedication Is On

January 21, 2012

We are going ahead with the dedication ceremony as planned for this Saturday at 1PM.

The houses will be open and have heat running in them.

The main part of the ceremony will be outside.

Thanks and see you there – Sue and Howard


Dedication Ceremony on 21-JAN-2012 (SAT) at 1PM

January 9, 2012

OUR Dedication Ceremony on 21-JAN-2012 (SAT) at 1PM.

See the details in the “Up Coming Events” tab


Fall 2011 – Winter 2011/2012

January 8, 2012

During AUG, SEP – we had to slow down our construction work on the build, as our fund raising efforts were lagging behind our needs to purchase the material needed for the build.

Still we were able to complete many of the items and managed to have more than enough work for our volunteers during this time.

In OCT-2011 – The Fuller Foundation made another significant contribution to this project.  These funds will allow us to accelerate the build work and drive to closure of construction.

During OCT, NOV, DEC – with the help of our regular volunteer construction crew and numerous other helpers.  We have made significant progress.

From mid summer to early winter – we have completed;

Insulation installed

Electrical wiring installed

Plumbing installed

Heating system installed

Septic system installed and inspected

Drywall installed

Drywall taped and plastered

Installation of interior doors and door and window trim.

Painting of interior

Started the installation of laminate flooring upstairs

We are well on our way to finishing the construction activities to allow for completion in late JAN-2012

———————————————————————–

Now with sufficient funds from our end of year appeal letter to Town of Boylston residents and the continued support of the Fuller Foundation.

We are driving to a completion of construction work by end of JAN 2012.  Which we now will achieve.

See “Up Coming Events” – For OUR Dedication Ceremony on 21-JAN-2012 (SAT) at 1PM.

The ongoing construction work that has been completed or will be in the next week;

Heating system inspected and turned on – YES heat in the house, finally!

Electrical and Plumbing inspected and turned on

Kitchen and Bath cabinets installed

Kitchen appliances being installed as we talk

Exterior work included the construction of 2 retaining walls

Exterior grading

Installation of ceramic tile in kitchens and bathroom floors.

To be done in the next week;

Finish tile work, finish installing light fixtures, sinks and plumbing fixtures

Install laminate flooring downstairs

Do a major cleaning

Prepare for the Dedication Ceremony on 21-JAN-2012

With the winter weather – we will have to come back and finish two last construction items;

Landscaping of the site

Paving the driveway and parking spots (we have spread gravel for the winter).

Thank you to all of the volunteers that have helped us get to this point.